Project: Walnut Creek Water Treatment Plant Filters Improvements

Owner: EBMUD

Bid Date: December 2nd, 2026 @ 2:00 P.M.

Engineer’s Estimate: $ 20 Mil - $25Mil 

Project Duration: 1250 CDs

 

We are requesting quotes from all qualified MBE/WBE/EMOB Subcontractors and Suppliers but not limited to:

CONCRETE MATERIAL, CONCRETE SUBS, CATHODIC PROTECTION, ELECTRICAL- BUILDING, PLASTIC PIPE, STEEL PIPE, PIPE SUPPLIERS, CONCRETE REPAIR, REINFORCING STEEL, PIPE SUPPORTS, MISC. METALS, ABESTOS ABATEMENT, PAINTING/COATINFS, VALVES/WATER MAIN/TEMP FACILITIES, DRAINAGE PUMPING EQUIPMENT, PUMPING PLANT ELECTRICAL , GENERATORS/SWITCH GEAR.

 

Project Description:

The scope of work includes but is not limited to;

1. Filters 1 through 4:

a. Demolish existing Wheeler Bottom underdrains.

b. Replace and provide new underdrains, troughs, media, stop logs, applied channel

overflow pipes, valves, and gaskets.

c. Demolish existing surface wash piping; furnish, install, and demolish temporary

surface wash piping. Furnish and install new air scour piping.

d. Furnish and install new lighting panel.

2. Filters 5 through 8:

a. Replace and provide new troughs and valves.

b. Investigate and repair the water leak at Filter 5 Right (5R) filter box. Replace all

media with new media in Filter 5R.

c. For Filters 5 through 8 except for Filter 5R, replenish lost media with new media

to the levels indicated in the design drawings.

d. Demolish Filter 5 & 7 Foundation Fieldbus, replace with District-furnished

instrumentation, and replace and rewire valve boards.

3. Pipe Gallery

a. Demolish Washwater Supply (WWS) tee, flow control valve (FCV), pipe loop

and supports. Furnish and install 24”/20” WWS bypass, supports and valves.

Provide new cross, valves, associated piping, and instrumentation.

b. Demolish polyblend tank, including concrete curbs.

4. Blower Building

a. Replace and provide new switchboard.

5. Operations Building

a. Furnish and install 800A Manual Transfer Switch (MTS) with generator

connection box. Reroute existing, replace and provide new cable.

 

Project information, including plans & specifications can be found by contacting:

estimating@mountaincascade.com


Subcontractors must possess a current contractor’s license, DIR number, insurance and worker’s compensation coverage. Subcontractors will be required to enter into our standard contract.

Mountain Cascade, Inc. is a Union Contractors and is signatory to Operating Engineers/Carpenters/Laborers/Teamsters.

Please feel free to contact Mountain Cascade, Inc. at 925.373.8370 with any questions concerning bonding, insurance, lines of credit, and job overview.  We look forward to your response.
 

Mountain Cascade Inc. is an Equal Opportunity Employer California License # 422496

 

 

This is Part of a Good Faith Outreach. Your response is greatly appreciated.


Mountain Cascade Inc. - Walnut Creek Water Treatment Plant Filters Improvements


Email To Friend

Your name
Your email *
Your friend's email *
Your message


« Go Back



SBE Northeast
 


Louisiana Business JournalArchive