High-Speed Rail Authority Completes Environmental Clearance into Bakersfield

 
11/19/2019

The California High-Speed Rail Authority (Authority) issued the Record of Decision for the final 23-mile route between Shafter and Bakersfield in the Central Valley.  This completes the state’s environmental review process between Fresno and Bakersfield and allows the Authority to move toward project construction into Bakersfield. This is the first major environmental action taken under the State’s newly granted federal National Environmental Policy Act (NEPA) and further emphasizes the Authority’s commitment to accelerate the project under new executive leadership.

“I’m proud of the collaborative and cooperative effort that went into this process.  Together with our local partners, we are prepared to move forward on project implementation into Bakersfield in a manner beneficial to the project, the city and the county,” said Authority CEO Brian Kelly. “We look forward to a continued partnership as we enter this next phase of the project.”

In order to finalize this environmental document and gather comprehensive feedback, the Authority held over 100 stakeholder meetings, 17 additional public and technical working group meetings, and 15 monthly regulatory agency coordination meetings.

The section receiving clearance extends from Shafter east towards State Route 99 and the existing Union Pacific Railroad tracks, then southward into Bakersfield, ending at a station location at F Street in downtown Bakersfield.  This builds upon analysis done previously in the region, narrowing down the specific alignment route that was most amenable to the local communities.

The document released today is a Final Supplemental EIS under NEPA. The document evaluates potential environmental effects of the Locally Generated Alternative, the alternative developed through city and state collaboration.  The associated federal approval document also issued today is a Supplemental Record of Decision. This federal approval is similar to the action the Authority’s Board of Directors took in October 2018 under the state’s California Environmental Quality Act (CEQA) for this project segment.

The Supplemental Record of Decision signed by CEO Brian Kelly and issued today is the first of several environmental documents expected to be released within the next 12 months.  In 2020, the Authority will release all six remaining draft environmental documents for public comment, on a schedule to complete the process (via Records of Decision) well ahead of the federal grant completion deadline. Such actions will keep the Authority on track to complete environmental clearance on the full 520-mile project which runs from San Francisco to Los Angeles/Anaheim.

 

Project
Segment

 
Draft
EIR/EIS

 
Revised
ROD Date

 
Months to ARRA 12/2022 Deadline from ROD Date
 
Locally Generated Alternative (F – B)*
*Complete
 
July 2019
 
October 2019
 
39
 
Central Valley Wye
(M – F)

 
September 2019
 
September 2020
 
27
 
Bakersfield to Palmdale
 
January 2020
 
February 2021
 
22
 
Burbank to Los Angeles
 
February 2020
 
January 2021
 
23
 
Palmdale to Burbank
 
February 2020
 
August 2021
 
16
 
San Jose to Merced
 
March 2020
 
April 2021
 
20
 
San Francisco to San Jose
 
April 2020
 
June 2021
 
18
 
Los Angeles to Anaheim
 
November 2020
 
December 2021
 
12
 

 SOURCE: https://www.hsr.ca.gov/communication/news_room/news_releases/?id=31