ADVERTISEMENT FOR BIDS
CITY & COUNTY OF SAN FRANCISCO
SAN FRANCISCO PUBLIC WORKS
Sourcing Event ID No.: 0000005517
CASTRO STATION ELEVATOR
(PW CASTRO STTN ELEV)

Bids shall be submitted online via ShareFile until 2:30:00 p.m. on Wednesday, June 15, 2022, after which the bid opening will be conducted live online via Microsoft Teams. Contract Administration will email the Microsoft Teams meeting information to all Plan Holders approximately 24 hours prior to Bid opening. Digital files of Bid Documents, Plan Holders Lists, and Addenda may be downloaded at no cost from the Public Works Electronic Bid Documents Download site at https://bsm.sfdpw.org/ContractAdmin/Login.aspx. Please visit the Contracts, Bids and Payments webpage at https://bidopportunities.apps.sfdpw.org for more information. Notices regarding Addenda and other bid changes will be distributed by email to Plan Holders.

Scope of Work: As part of a larger San Francisco Municipal Transportation Agency (SFMTA) system-wide effort to improve accessibility of the MUNI subway system, the Castro Station will undergo several upgrades in and around the station area to improve ADA access to the station and transit services. The Castro Station Elevator Project will add a second elevator to the station to provide continuous access to the station and trains. The 4-stop elevator design includes a translucent etched pattern on clear laminated glass façade to provide unobstructed sightline into the elevator cab to improve rider safety. To create a safer and ADA compliant paths of travel, the brick paving area around the station entrance at street and Concourse levels will be regraded. A portion of the sidewalk on Market Street will be made wider, and new curb ramps will be added at Market and Collingwood Streets. The existing plaza lighting will be replaced, the terraces at the Concourse level will be re-planted, and new fences and bench will be installed.

The time allowed for completion is 600 consecutive calendar days. The estimated construction cost is approximately $12,000,000. For more information, contact the Project Manager Ben Wu by phone: (415) 646 2690 direct, (415) 905-0214 cell, or email: Ben.Wu@sfmta.com.
On July 1, 2014, the registration program under section 1725.5 of the California Labor Code went into effect. The program requires that all contractors and subcontractors who bid or work on a public works project register and pay an annual fee to the California Department of Industrial Relations (“DIR”).
No contractor or subcontractor may be listed in a bid or awarded a contract for a public works project unless registered with the DIR as required by Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
This Project shall incorporate the required partnering elements for Partnering Level 3. Refer to Section 01 31 33 for more details.
Pursuant to San Francisco Administrative Code (“Administrative Code”) Section 6.25 and Chapter 25 of the Environment Code, “Clean Construction” is required for the performance of all work.
This Contract is subject to the requirements of Administrative Code Chapter 12X, which prohibits contracting in states with laws that allow discrimination. The City is prohibited from entering into any Contract with a Contractor that has its United States headquarters in a state on the Covered State List or where any or all of the work on the contract will be performed in any of those states on the Covered State List. Administrative Code Chapter 12X and a list of states on the Covered State List can be found at: http://sfgsa.org/chapter-12x-anti-lgbt-state-ban-list.
The Specifications include liquidated damages. Contract will be on a Lump Sum Bid Items basis. Progressive payments will be made.
The Contract will be awarded to the lowest responsible responsive bidder.

A bid may be rejected if the City determines that any of the bid item prices are materially unbalanced to the potential detriment of the City.

Bid discounts may be applied as per Administrative Code Chapter 14B. LBE Subcontracting Participation Requirement is 20%. For details, contact Ivan Oldenkamp by phone at (415) 515-6793 or by email at ivan.oldenkamp@sfgov.org. In accordance with Administrative Code Chapter 14B requirements, all bidders shall submit documented good faith efforts with their bids, except those who exceed the above stated LBE Subcontracting Participation Requirement by 35%. Bidders must achieve 80 out of 100 points to be deemed responsive. Bidders will receive 15 points for attending the pre-bid conference, if scheduled. Refer to CMD Form 2B.
An online pre-bid meeting will be held on Tuesday, May 3, 2022 at 2:30 PM via Microsoft Teams Meeting web conference:

Join on your computer or mobile app
Click here to join the meeting
Or call in (audio only)

+1 415-906-4659,,646469927# United States, San Francisco
Phone Conference ID: 646 469 927#

For information on the City’s Contractor Development Program, call (415) 986-3999 or email cdp@imwis.com
A corporate surety bond or certified check for ten percent (10%) of the amount bid must accompany each bid. Administrative Code Section 6.22(a) requires all construction greater than $25,000 to include performance and payment bonds for 100% of the contract award.
Class "B" license is required to bid.
In accordance with Administrative Code Chapter 6, no bid is accepted and no contract in excess of Threshold is awarded by the City and County of San Francisco until such time as the Mayor or the Mayor’s designee approves the contract for award, and the Director of Public Works then issues an order of award. Pursuant to Charter Section 3.105, all contract awards are subject to certification by the Controller as to the availability of funds.
Minimum wage rates for this project must comply with the current General Prevailing Wage as determined by the State Department of Industrial Relations. Minimum wage rates other than applicable to General Prevailing Wage must comply with Administrative Code Chapter 12P, Minimum Compensation Ordinance. In addition, the San Francisco Citywide Project Labor Agreement (PLA) became effective on July 14, 2020. This Contract is a Covered Project and Bidders are advised that the PLA is incorporated into the contract documents. More information about the PLA can be found at: https://sfgov.org/olse/citywide-project-labor-agreement.

This Project is subject to the requirements of the San Francisco Local Hiring Policy for Construction (''Policy'') as set forth in Administrative Code Section 6.22(g). Bidders are hereby advised that the requirements of the Policy will be incorporated as a material term of any contract awarded for the Project. Refer to Section 00 73 30 of the Project Manual for more information.
Bidders are hereby advised that the Contractor to whom the Contract is awarded must be certified by the Contract Monitoring Division as being in compliance with the Equal Benefits Provisions of Chapter 12B of the Administrative Code within two weeks after notification of award.

If a bidder objects on any ground to any bid specification or legal requirement imposed by this Advertisement for Bids, the bidder shall, no later than the 10th working day prior to the date of Bid opening, provide written notice to the Contract Administration Division, San Francisco Public Works, setting forth with specificity the grounds for the objection.
Right reserved to reject any or all bids and waive any minor irregularities.

4/28/22
CNS-3577878#
SMALL BUSINESS EXCHANGE

SF DPW - CASTRO STATION ELEVATOR (PW CASTRO STTN ELEV)


Email To Friend

Your name
Your email *
Your friend's email *
Your message


« Go Back



SBE Northeast
 


Louisiana Business JournalArchive